(4) If the total working hours were 100,which of the following tasks will account for approximately

find all question on www.blogpoints.net and www.allentrance.blogpoints.net
   
Question :
(4) If the total working hours were 100,which of the following tasks will account for approximately 50 hours ?
A A. Coding
   
B B. Design
   
C C. Offshore testing
   
D D. Offshore testing plus design
   
  Answer:A